Proving Delay And Damages: Lessons On Critical Path Analysis And Insurance Recovery In Dependable Mechanical V Ledcor

Singleton Urquhart Reynolds Vogel LLP
Singleton Urquhart Reynolds Vogel LLP
Contributor
Singleton Urquhart Reynolds Vogel LLP

Singleton Urquhart Reynolds Vogel LLP

Singleton Urquhart Reynolds Vogel LLP is a Canadian national law firm that specializes in the...

View firm profile
Explore more from Singleton Urquhart Reynolds Vogel LLP

It is a truism in the construction industry that a project will, outside of exceptional circumstances, encounter some sort of delay.

CanadaReal Estate and Construction

It is a truism in the construction industry that a project will, outside of exceptional circumstances, encounter some sort of delay. These delays can and often do result in claims which, where not negotiable or otherwise resolved, can result in a dispute. Such claims are often challenged in court and can be subject to significant scrutiny.

In Dependable Mechanical Systems Inc v Ledcor Construction Limited, 2025 ONSC 5100 ("Dependable Mechanical"), the Superior Court provided certain reminders on the standard of fact and expert evidence required to prove a delay claim, as well as the applicability of insurance policies to the calculation of damages. This decision offers several practical takeaways for contractors, subcontractors, and construction managers.