ARTICLE · 01 JUNE 2023

PPCLA Transition Periods: What This Means For The Construction Industry

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

The Prompt Payment and Construction Lien Act (the PPCLA) is now law in Alberta. In addition to creating uncertainty around prompt payment, invoicing and adjudication...

CanadaReal Estate and Construction

The Prompt Payment and Construction Lien Act (the PPCLA) is now law in Alberta. In addition to creating uncertainty around prompt payment, invoicing and adjudication, the PPCLA's transition provisions are likely to generate uncertainty in the construction industry.

The PPCLA and associated regulations contain rules that govern the transition from the former Builders' Lien Act (the BLA) to the PPCLA. Sections 74(1)(2) and (3) of the PPCLA provide that:

  • The PPCLA applies to any contract or subcontract entered into on or after Aug. 29, 2022, which is the date when the PPCLA came into force in Alberta; and
  • contracts that were executed before Aug. 29, 2022, must be amended to comply with the PPCLA within two years, if they are still in progress at that time.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.