Ontario's New Construction Act – Good For The Industry!

The Construction Act has received Royal assent. It is expected that the proclamations necessary to bring it into force will occur this spring.

CanadaReal Estate and Construction

The Construction Act has received Royal assent. It is expected that the proclamations necessary to bring it into force will occur this spring. This is a radical departure from our Construction Lien Act, in effect for over 30 years. Changes important to the construction industry in the Construction Act include the following:

Construction liens – The time period for preserving a construction lien is extended from 45 days to 60 days. The time period for perfecting the lien (starting the court action) is extended from 45 days to 90 days.

A certificate of substantial performance must accurately set out the legal description of the property against which a construction lien may be registered, including the legal property description and PIN.