How Long Do You Have To Preserve A Construction Lien?

A construction lien can be a powerful tool to assist with the collection of invoices for the supply of services or materials to an improvement to a property.

CanadaReal Estate and Construction

A construction lien can be a powerful tool to assist with the collection of invoices for the supply of services or materials to an improvement to a property.

Under the Construction Act, the first step to take to obtain the benefit of a construction lien in Ontario is to preserve the lien by registering it against title to the subject property. The Ontario Construction Act imposes a strict 60-day time limit within which this step has to be taken.

Because the preservation period is so short, it is crucial to know exactly what events can trigger the 60-day period in order to know when the 60-days to register the lien will run out.

Triggering Events

For a general contractor who contracts directly with the owner, the following events can trigger the preservation period:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from