The second round of major revisions to Ontario's Construction Act came into force on Oct. 1, 2019, ushering in statutory prompt payment provisions and mandatory adjudication.

CanadaReal Estate and Construction

This article was originally published in the Builder Bites Newsletter by Building Excellence (www.buildingexcellence.ca).

The second round of major revisions to Ontario’s Construction Act came into force on Oct. 1, 2019, ushering in statutory prompt payment provisions and mandatory adjudication.

Need for prompt payment

Although industry standard payment terms are 30 to 45 days, actual payment regularly exceeds 70 days. These unsustainable delays mandate a fresh approach.

The new process starts when the contractor gives the owner a prescribed “proper invoice,” which includes many of the details contractors already have in their invoices. Contractors must render invoices every 30 days, unless otherwise agreed.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be ought about your specific circumstances.

See more popular content from