Alberta Court Clarifies Entitlement To Public Works Act Payments In Recent Ruling

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP ("Miller Thomson") is a national business law firm with approximately 500...

View firm profile
Explore more from Miller Thomson

When multiple parties contribute to a public construction project, but not all get paid, which of these parties has the legal right to claim unpaid funds? This question recently...

CanadaReal Estate and Construction

Introduction

When multiple parties contribute to a public construction project, but not all get paid, which of these parties has the legal right to claim unpaid funds? This question recently came before the Alberta Court of King's Bench in a rare and significant decision interpreting the Public Works Act, RSA 2000, c P-46 (the "PWA").

In Alberta Social Housing Corporation v Dawson Wallace Construction Ltd., the Court allowed the appeal of a General Contractor and dismissed the competing claims of two "Subsubcontractors." The decision is noteworthy as there is minimal judicial interpretation of the PWA, and it specifically bars submitted PWA claims of subsubcontractors on the basis of a strict interpretation of Section 14 of the PWA, which only refers to "contractors" and "subcontractors."

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from