Aecon Buildings, a Division of Aecon Construction Group Inc. v. Brampton (City)

A dispute between the City of Brampton and Aecon Buildings arose over the construction of the $46-million Brampton Performing Arts Centre. Aecon claimed damages for breach of contract arising from delays in construction.

CanadaReal Estate and Construction

[2010] O.J. No. 5630 (C.A.) (Released 24 December 2010)

Civil procedure – Third party procedure – Discovery – Production and inspection of documents – "Mary Carter"-type Settlements – Immediate Disclosure

A dispute between the City of Brampton and Aecon Buildings arose over the construction of the $46-million Brampton Performing Arts Centre. Aecon claimed damages for breach of contract arising from delays in construction.

Following Aecon's commencement of its action, the two parties came to an agreement. The City of Brampton agreed to advance claims against a third party architect on Aecon's behalf and Aecon agreed to cap its damage claims against the City of Brampton to any amounts the City recovered from the third party architect and its consultants (the "agreement").