The Construction Lien Amendment Act was passed in
December 2017 and substantively changed the Construction Lien
Act, now the Construction Act (the
"Act "). Its primary purposes
were to: (i) modernize the existing Construction Lien Act;
(ii) provide prompt payment legislation throughout Ontario; and
(iii) introduce adjudication provisions for disputes arising in the
course of a contract. For further information on the
Construction Act see our June 20, 2018 Update, Construction Act: Here We Go!, as well as our
December 17, 2018 Update, Bill 57 and Amendments to the Construction
Act.
Adjudication
One of the most significant changes introduced in the
Act is an adjudication regime to resolve disputes on
construction projects as they arise in the course of the project,
rather than at the end of a project.