When Can A Quebec Court Overlook An "Entire Agreement Clause"?

The parties negotiated a complex contract, later amended.

CanadaLitigation, Mediation & Arbitration

Invenergy Wind Canada v. Éolectric Inc., 2019 QCCA 1073

http://canlii.ca/t/j138b

Invenergy produces and sells electricity generated by wind towers. Éolectric finds suitable sites, maps them, obtains regulatory approvals and then collects royalties from Invenergy.

The parties negotiated a complex contract, later amended. A dispute arose as to Éolectric's entitlement to certain payments pertaining to electricity produced in additional sites.

The contract contains an « entire agreement clause » and Invenergy is adamant that this prevents the court from reading into the contract additional terms having the effect of varying the expressed intent.  The Court of Appeal reminds us here that the civil law is based on the primacy of the negotium (the contents of the contract) over the instrumentum (the material form of the contract).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from