It was for the arbitrator, not
the court, to interpret and apply the substantive provisions of the
[agreement], and it is of no moment whether the arbitrator did so
reasonably or unreasonably, correctly or incorrectly.1
The Ontario Court of Appeal has once again confirmed that
section 46(1) of the Arbitration Act, 19912 (the
"Act") is not an alternate appeal route and must not be
treated as such. In Alectra Utilities Corporation v. Solar
Power Network Inc.,3 the Court of Appeal reversed the
decision of a judge who did just that by finding that the
arbitrator's interpretation of the agreement in issue was
unreasonable and that, therefore, the arbitrator's award was
made in excess of his jurisdiction under the agreement. In other
words, the application judge determined that an unreasonable
interpretation or incorrect interpretation of an agreement was a
jurisdictional error that permitted the court to set aside the
award under paragraph 46(1)3 of the Act.