Court Rejects Staying Your Own Action In Favour Of An Arbitration Process

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

10060 Jasper Avenue Building Limited and WIR Equities Inc. (Jasper) sued Scotia Place Tower III Inc. (Scotia) for amounts owing for maintenance conducted on a property...

CanadaLitigation, Mediation & Arbitration

10060 Jasper Avenue Building Limited and WIR Equities Inc. (Jasper) sued Scotia Place Tower III Inc. (Scotia) for amounts owing for maintenance conducted on a property owned and operated by the Parties. Operation and management of the property was governed by two agreements between Jasper and Scotia: an Owners Agreement and a Management Agreement (Agreements). Both Agreements included a permissive dispute resolution process (Dispute Process) for issues arising between Jasper and Scotia.

Jasper brought a Notice of Default pursuant to the Agreements. Scotia's responding Notice of Objection confirmed the dispute, argued for referral to an "expert" pursuant to the Dispute Process and nominated an expert. Scotia was clear that its Notice of Objection and its expert nomination were made without prejudice to its right to argue the matter should be heard in another forum, including in the Alberta Courts. Scotia confirmed the Notice of Objection was filed solely in the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from