On November 16, 2022, by ministerial letter, the Honourable Dan
Vandal, in his role as Minister of Northern Affairs, and on behalf
of the Ministers of Environment and Climate Change, Fisheries,
Oceans and the Canadian Coast Guard, Natural Resources, and
Transport, accepted the recommendation of the Nunavut Impact Review
Board, denying Baffinland Iron Mines Corporation its approval for
the Phase 2 expansion of the Mary River Mine.
Baffinland operates the Mary River Project under its 2012
approval which set a nominal production rate of 18 Million tons of
iron ore per year. The Project includes a mine site and two ports,
Milne Port and Steensby Port, a haul road, and a railroad. A 2014
modification was approved to allow extraction of up to an
additional 4.2 Mtpa of iron ore for truck transport to Milne Port
while additional infrastructure was being constructed.