Divisional Court Overturns Environmental Review Tribunal Decision And Allows Wind Project To Proceed

In an important decision for stakeholders in the Ontario renewable energy industry, the Divisional Court of Ontario overturned the July 2013 decision by the Environmental Review Tribunal in Ostrander Point.

CanadaEnvironment

In an important decision for stakeholders in the Ontario renewable energy industry, the Divisional Court of Ontario overturned the July 2013 decision by the Environmental Review Tribunal (the ERT) in Ostrander Point. In its July 2013 decision, the ERT had, for the first time, revoked a Renewable Energy Approval (REA) issued by the Ontario Ministry of the Environment (MOE) authorizing Ostrander Point GP Inc. (Ostrander) to construct and operate nine wind turbines on a site in Prince Edward County (the Project). The ERT's decision was based solely on its determination that the Project would cause serious and irreversible harm to an endangered species, the Blanding's Turtle, which had been identified in the area. All other grounds of appeal by the Prince Edward County Field Naturalists (PECFN) and the Alliance to Protect Prince Edward County (APPEC), i.e., alleged impacts to human health and to other animal and plant species, had been dismissed.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from