COVID-19 Delays Ontario's New Excess Soil Regime

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

Ontario's comprehensive excess soil management regime was set to be phased in starting July 1, 2020, much to the anticipation of the land development industry, municipalities, landowners, and consultants.

CanadaEnvironment

Ontario's comprehensive excess soil management regime was set to be phased in starting July 1, 2020, much to the anticipation of the land development industry, municipalities, landowners, and consultants. The implementation of the first phase of the new excess soil regime is now pushed back to January 1, 2021, due to the COVID-19 outbreak.

What you need to know

  • The On-Site and Excess Soil Management Regulation (Excess Soil Regulation) creates new obligations for persons ultimately responsible for projects involving the excavation of soil, including any site alteration, construction of a building or infrastructure, or sediment removal.
  • The Excess Soil Regulation was filed on December 4, 2019, and is set to come into effect in a phased approach, beginning on July 1, 2020.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Please add at the end of every article before the disclaimer (remember to change the article id):

About BLG

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from