On July 11, 2012 Ontario’s Minister of Energy issued a directive (directive) to the Ontario Power Authority (OPA) clarifying certain policies and slightly adjusting the feed-in tariff (FIT) program rules and contract.

CanadaEnergy and Natural Resources

Introduction

On July 11, 2012 Ontario's Minister of Energy issued a directive (directive) to the Ontario Power Authority (OPA) clarifying certain policies and slightly adjusting the feed-in tariff (FIT) program rules and contract. The directive was issued following the Ontario government's review of feedback regarding the draft rules, contract forms and definitions for the revised FIT 2.0 program issued in April of this year.

Summary of the Directive's Key Points:

i. Prioritization of Community and Aboriginal Participation Projects

The ministerial directive clarified that the OPA will prioritize applications for projects with (a) greater than 50 per cent community equity interest held by a co-operative with at least 50 members being local property owners, or (b) greater than 50 per cent Aboriginal equity participation. With respect to the contract capacity set aside for projects with at least  50 per cent community or Aboriginal equity participation, the OPA