Latest Updates On Ontario's Long Lead-Time Request For Proposals

Blake, Cassels & Graydon LLP
Blake, Cassels & Graydon LLP
Contributor
Blake, Cassels & Graydon LLP

Blake, Cassels & Graydon LLP

As one of Canada’s top business law firms, Blake, Cassels & Graydon LLP (Blakes) provides...

View firm profile
Explore more from Blake, Cassels & Graydon LLP

This is the latest on the Independent Electricity System Operator (IESO) Long Lead-Time Request for Proposals (LLT RFP).

CanadaEnergy and Natural Resources

This is the latest on the Independent Electricity System Operator (IESO) Long Lead-Time Request for Proposals (LLT RFP). The LLT RFP aims to address growing demand in Ontario's electricity sector by securing energy and capacity resources with longer lead times for project development.

Background

The IESO began engaging with stakeholders on the design of the LLT RFP in April 2025, following the issuance of the Long Lead-Time Request for Information (LLT RFI) in 2024. The IESO submitted the LLT RFI results to the Ministry of Energy (Ministry) on August 29, 2025.

Eligibility

The LLT RFP is a reliability-based procurement intended to secure incremental energy and capacity from new-build resources with a lead time of five or more years that will contribute to system needs over a 40-year term.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

For permission to reprint articles, please contact the [email protected] Marketing Department.

© 2026 Blake, Cassels & Graydon LLP.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from