ERT Revokes Renewable Energy Due To Airport Impacts

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

McCarthy Tétrault LLP provides a broad range of legal services, delivering strategic and...

View firm profile
Explore more from McCarthy Tétrault

As noted, this was the first ERT decision to revoke an REA based on the finding of harm to human health.

CanadaEnergy and Natural Resources

As we reported in a blog post in October 2016, the Renewable Energy Approval ("REA") for the Fairview Wind Farm ("Fairview") in Clearview Township was revoked by the Environmental Review Tribunal ("ERT") on the basis that the project would cause serious and irreversible harm to the endangered species of bat, the little brown bats. The ERT also concluded, for the first time, that there would be harm to human health due to close proximity of the project to the Collingwood Airport and the Clairview Field Airport.

The ERT granted a request from Fairview to address remedies with respect to the finding of serious and irreversible harm to the little brown bats through further submissions at a remedy hearing. Fairview did not request such hearing for the finding on harm to human health. In the remedy hearing, the ERT had to determine, under s. 145.2.1(4) of the Ontario Environmental Protection Act (1990) ("EPA"), whether to (a) revoke the decision granting the REA, (b)