Court Of Appeal Upholds AUC's View On "Stranded Assets"

In 2011, the Alberta Utilities Commission ("AUC") issued its decision in the Generic Cost of Capital ("GCOC") proceeding.

CanadaEnergy and Natural Resources

In 2011, the Alberta Utilities Commission ("AUC") issued its decision in the Generic Cost of Capital ("GCOC") proceeding. In 2013, the AUC issued its decision in the Utility Asset Disposition ("UAD") proceeding. Both decisions considered the issue of "stranded assets".

Stranded assets are those utility assets that, while still in service, become incapable of being used because of some extraordinary event. The existence of stranded assets, in the context of a regulated utility, gives rise to an important question: who bears the loss of the asset which is not fully depreciated but which is incapable of use? The AUC, in the aforementioned decisions, concluded that utility shareholders, and not ratepayers, bear the risk of holding stranded assets.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from