ARTICLE · 03 MARCH 2022

Zerbin v Vrbanek, 2021 ABCA 317: The Alberta Court Kicks Back At A Contractor Taking Kickbacks

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP ("Miller Thomson") is a national business law firm with approximately 500...

View firm profile
Explore more from Miller Thomson

In the Alberta Court of Appeal decision, Zerbin v Vrbanek, 2021 ABCA 317 ("Zerbin"), and the preceding trial decision (Zerbin v Vrbanek, 2020 ABQB 797),

CanadaCriminal Law

In the Alberta Court of Appeal decision, Zerbin v Vrbanek, 2021 ABCA 317 ("Zerbin"), and the preceding trial decision (Zerbin v Vrbanek, 2020 ABQB 797), the Alberta Courts assessed damages against a general contractor who was bleeding the owners on a project for excess funds by illegal means.

Background

The plaintiff owners in this case, David and Barbara Zerbin, wanted to build their "dream home" - a multi-million dollar property - along with a second home on a nearby lot for their daughter. To this end the Zerbins hired DN Developments (carrying on business as Darren's Homes) and Mr. Vrbanek, the sole shareholder, director, and principal of DN Developments, to provide project management services. Under the project management agreements, DN Developments was to provide its services on a "cost-plus" basis - there was no hard ceiling on the cost, and DN Developments' service charge was 20.96 percent. For the sake of expediency, the Zerbins agreed that DN

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from