Province Reimposes Limitation Periods And Lien Timelines Under The Construction Act

Blaney McMurtry LLP
Blaney McMurtry LLP
Contributor
Explore more from Blaney McMurtry LLP

On March 17, 2020, in response to the COVID-19 pandemic, the Government of Ontario declared an emergency under the Emergency Management and Civil Protection Act. On March 20, 2020, Ontario passed a regulation under that Act...

CanadaCoronavirus (COVID-19)

On March 17, 2020, in response to the COVID-19 pandemic, the Government of Ontario declared an emergency under the Emergency Management and Civil Protection Act. On March 20, 2020, Ontario passed a regulation under that Act (the "Limitation Suspension Regulation") to, among other things, temporarily suspend limitation periods in the Province, retroactive to March 16, 2020. The Limitation Suspension Regulation applies to "[a]ny provision of any statute, regulation, rule, by-law or order of the Government of Ontario that establishes any period of time within which any step must be taken in any proceeding in Ontario...".1

Over the last three weeks, many contractors have received notices from owners or owners' agents taking the position that they are prohibited from paying out holdback upon the completion of contracts given the Limitation Suspension Regulation. The owners' position is that paragraph 2 of the Limitation Suspension Regulation suspends the time within which

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be ought about your specific circumstances.

See more popular content from