Share on LinkedInShare on LinkedIn

ARTICLE · 16 DECEMBER 2022

Force Majeure Clauses: Ontario Superior Court Clarifies Covid-19 Impact On Contract Performance Obligations

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

The COVID-19 pandemic created new and unanticipated operating challenges for businesses around the world. The pandemic caused many businesses to significantly scale down operations...

CanadaCoronavirus (COVID-19)

The COVID-19 pandemic created new and unanticipated operating challenges for businesses around the world. The pandemic caused many businesses to significantly scale down operations, or to cease operations all together. It was no surprise to litigators that contracting parties would invoke force majeure clauses in their contracts in response to the pandemic's significant effect on business operations.

On Oct.19, 2022, the Ontario Superior Court of Justice released its decision in Porter Airlines Inc. v. Nieuport Aviation Infrastructure Partners GP, 2022 ONSC 5922, where it considered whether the pandemic engaged the force majeure clause in a License Agreement between Porter Airlines Inc. ("Porter") and Nieuport Aviation Infrastructure Partners ("Nieuport"). The Court also considered whether Nieuport acted in a "commercially reasonable" manner in exercising its contractual rights under the License Agreement.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from