Determining whether purported “change in law” claims
resulting from the COVID-19 pandemic will be successful is not
straightforward. Some construction contracts (for example, GC
10.2.7 of CCDC 2) permit claims where changes are made to laws,
rules, regulations or codes that affect the cost of work under that
contract. Parties may therefore try to argue that certain
provincial COVID-19-related Orders and/or legislation are caught by
these types of “change in law” provisions in their
construction contracts, triggering a potential entitlement to a
claim for monetary compensation. In many circumstances, however,
the better view may be that this is not in fact the case. Any
analysis will ultimately hinge on whether or not a “change in
law” has in fact occurred.