The UK government has sought to address the specific challenges the COVID-19 pandemic presents for PFI and PPP contracts through two Guidance Notes.

CanadaCoronavirus (COVID-19)

The UK government has sought to address the specific challenges the COVID-19 pandemic presents for PFI and PPP contracts through two Guidance Notes. In this note we examine how (and how well) this guidance address the real issues for the public sector and PFI/PPP Contractors?

What is the government doing to support suppliers?

The Infrastructure and Projects Authority ("IPA") issued a Guidance Note detailing how public bodies can support PFI and PF2 projects on 2 April 2020. This supplements the more general Cabinet Office Procurement Policy Note on supplier relief due to COVID-19. Both Guidance Notes took effect immediately and (at the moment) apply until 30 June 2020.

Both notes recognise that PFI and PF2 contractors are vital to the delivery of public services, especially in response to COVID-19, and the need for Contractors to have contingency plans to allow services to continue. The guidance recognises that in present circumstances the underlying contract

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from