Following Ontario's recent Order suspending limitation and procedural time periods, there has been some uncertainty regarding whether liens in Ontario continue to expire in the ordinary course. The Attorney General...

CanadaCoronavirus (COVID-19)

Following Ontario's recent Order suspending limitation and procedural time periods, there has been some uncertainty regarding whether liens in Ontario continue to expire in the ordinary course. The Attorney General has now confirmed that they do.

On March 20, 2020, the Ontario Government issued an Order under Subsection 7.1(2) of the Emergency Management and Civil Protection Act suspending limitation periods and procedural time periods in Ontario (the "Suspension Order"). It was initially unclear whether the Suspension Order applied to the timelines established under the Construction Act, formerly the Construction Lien Act (the "Act"). Many in the construction industry were concerned about the impact of the Suspension Order on the flow of funds on construction projects. If the Suspension Order had applied to lien periods, the holdback period established under the Act would not expire, and holdback funds could not be released. Undoubtedly this would have put

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from