Legal Update: Remoteness Of Damages For Breach Of Contract

In Attorney General of the Virgin Islands v Global Water Associates Ltd (British Virgin Islands) [2020] UKPC 18 ("GWA") the Privy Council, the Island's final appeal Court...

British Virgin IslandsCorporate/Commercial Law

In Attorney General of the Virgin Islands v Global Water Associates Ltd (British Virgin Islands) [2020] UKPC 18 ("GWA") the Privy Council, the Island's final appeal Court, has recently reaffirmed the test for remoteness of damages in breach of contract claims.

In such a claim, a party will only be able to recover damages which:-

  • Arise naturally from the breach of contract; or
  • Are in the reasonable contemplation of the parties at the time of contracting.

It is this second limb which invokes a remoteness test, meaning that damages can only be claimed if they are reasonably foreseeable.

The Facts

In GWA the Government of the British Virgin Islands ("BVI") had entered into two contracts with Global Water Associates ("Global"). The first being for Global to design and build a water reclamation treatment plant (the "D&B Agreement") and the second being for Global to manage, operate and maintain the said plant for 12 years once built (the "Management