In Attorney General of the Virgin Islands v Global
Water Associates Ltd (British Virgin Islands) [2020]
UKPC 18 ("GWA") the Privy Council,
the Island's final appeal Court, has recently reaffirmed the
test for remoteness of damages in breach of contract claims.
In such a claim, a party will only be able to recover damages
which:-
- Arise naturally from the breach of
contract; or
- Are in the reasonable contemplation
of the parties at the time of contracting.
It is this second limb which invokes a remoteness test, meaning
that damages can only be claimed if they are reasonably
foreseeable.
The Facts
In GWA the Government of the British Virgin Islands
("BVI") had entered into two contracts
with Global Water Associates ("Global").
The first being for Global to design and build a water reclamation
treatment plant (the "D&B
Agreement") and the second being for Global to
manage, operate and maintain the said plant for 12 years once built
(the "Management