National Grid Electricity System Operator (ESO) and National Grid Electricity Transmission (NGET) have concluded the two-step grid connections offer process, having issuing final revised connection offers...

BelgiumEnergy and Natural Resources

National Grid completes two-step grid connection offer process

National Grid Electricity System Operator (ESO) and National Grid Electricity Transmission (NGET) have concluded the two-step grid connections offer process, having issuing final revised connection offers to all customers joining the connections queue between the initiative's inception at the end of February 2023 and 1 March 2024.

The temporary two-step process was designed to accompany the roll out of new Construction Planning Assumptions (CPAs) containing updated modelling assumptions to reflect more realistic analysis in respect of drop-out rates for projects in the connections queue, and the impact of batteries on the transmission network. Under the former CPAs the assumption was that the majority of projects in the queue would be delivered, when typically only between 30 and 40% of projects connect.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from