The recent case of BMD Major Projects Pty Ltd v Victorian Urban Development Authority represents a victory for contractors making latent conditions claims under the Australian Standards contracts. It also raises some interesting issues for both owners and contractors when dealing with latent conditions claim.

AustraliaReal Estate and Construction
Greg Richards
Greg Richards
Karen Beattie
Karen Beattie

The recent case of BMD Major Projects Pty Ltd v Victorian Urban Development Authority represents a victory for contractors making latent conditions claims under the Australian Standards contracts. It also raises some interesting issues for both owners and contractors when dealing with latent conditions claim.

The Victorian Urban Development Authority (VicUrban) intended to develop a disused quarry as a residential estate. Mining debris left spread across the site meant substantial excavation work was needed and BMD was contracted to undertake the work under a contract based on the Australian Standards construction contract, AS 2124 1992. As the works progressed BMD claimed the natural surface level of the site was lower than it could have reasonably anticipated and argued this was a latent condition.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from