When does a development consent lapse in NSW?

A development consent, Council permission to carry out development, lapses after five years if no physical commencement.

AustraliaReal Estate and Construction

What is a development consent?

Development consent is permission from a Council to carry out development on land.

When does a development consent lapse?

A development consent lapses five years after the date from which it operates (s95(1) of the Environmental Planning and Assessment Act 1979)(EPAA). This doesn't mean that the whole development covered by the development consent needs to be finished in the five year period to prevent the development consent from lapsing.

Are there any cases where my development consent won't lapse?

Section 95(4) and (5) of the EPAA provides that development consent for the erection of a building or the subdivision of land or the carrying out of work does not lapse if building, engineering or construction work relating to the building, subdivision or work is physically commenced on the land before the date on which the consent would otherwise lapse.