ARTICLE · 06 MAY 2019

When a section 34 agreement to a development application in NSW can be invalid

No consent by the land owner and a failure to record reasons can result in a lack of LEC jurisdiction to approve the DA.

AustraliaReal Estate and Construction

Recently the Court of Appeal held that a section 34 agreement (and subsequent approval by the Court) was invalid for two reasons:

  1. An owner of land affected by the DA did not provide consent; and
  2. The Commissioner failed to indicate in her judgment that she had considered a clause 4.6 request relating to the development.

While both these grounds may seem fairly obvious, as always there is more to the story.

No consent and failure to record reasons result in lack of jurisdiction

Both deficiencies above remove the jurisdiction of the Land and Environment Court ('LEC') to consent to the proposed development. The LEC can only approve a decision or agreement reached between the parties that is a decision that the court could have made in the proper exercise of its functions.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from