ARTICLE · 21 AUGUST 2012

Towers v Building and Development Dispute Resolution Committee & Ors [2012] QPEC 13

This was a challenge to a decision of the Building and Development Dispute Resolution Committee, which was out of time.

AustraliaReal Estate and Construction

Application to strike out proceedings – appeal from Building and Development Dispute Resolution Committee commenced out of time – Application for extension of time – whether grounds contained in appeal are valid grounds – s.39A Acts Interpretation Act 1954 – s.497 Sustainable Planning Act 2009

Facts: Mr Towers sought to challenge a decision of the Building and Development Dispute Resolution Committee regarding the siting of a structure on premises. Mr Towers had filed an Originating Application which sought both an extension of time in which to appeal, and Orders allowing the appeal.

The Council had filed an Application seeking Orders that Mr Towers' proceedings be struck out. It relied on three grounds. Firstly, that Mr Towers was out of time to institute an appeal; secondly, that he had not identified any appropriate grounds sufficient to warrant an extension of time within which to institute an appeal; and thirdly, that the grounds were not valid grounds of