Share on LinkedInShare on LinkedIn

ARTICLE · 15 DECEMBER 2014

Take another swing - Can you serve a second payment claim if the adjudicator's decision regarding similar claims was declared void?

Contractors should consider serving a payment claim under BCIPA even if an adjudication decision has been declared void.

AustraliaReal Estate and Construction

Article by Riki Kerr

The Building and Construction Industry Payments Act 2004 ("BCIPA") remains a powerful tool for contractors in the recovery of payment for their works.The Queensland Supreme Court recently in Civil Mining & Construction Pty Ltd -v- Isaac Regional Council [2014] QSC 231 once again reinforced this point in its consideration of the validity of a payment claim in the face of a previous payment claim of same fact being declared void and the matter concurrently being dealt with under the mechanisms provided in the contract.

Background

Civil Mining & Construction Pty Ltd ("CMC") and the Isaac Regional Council (the "Council") entered into a contract for road works construction. As part of the many disputes that occurred throughout the construction CMC served a payment claim under BCIPA (described as payment claim 8).In considering payment claim 8the adjudicator awarded CMC $9,923,090.87 of the $20,063,438.16 claimed. The Council in response applied