How Do You Overcome Processing Delays – Ask the Minister

The development industry and the LGAQ continue to disagree about processing times for Development Applications. I have never seen a Development Application processed within 12 weeks, either before or after the introduction of the Integrated Planning Act 1997.

AustraliaReal Estate and Construction

David Nicholls, Partner

The development industry and the LGAQ continue to disagree about processing times for Development Applications. The Executive Director of the LGAQ, Mr Greg Hallam, in a recent letter to the editor of The Courier Mail said:

"The average processing time for a properly completed development application in southeast Queensland is 12.2 weeks (LGAQ survey of development applications 2007). It is important to realise that many developers submit poorly made applications that require requests for additional information (40 per cent)."

As an objective observer, I consider this statement to be misleading. I can say without a shadow of a doubt that I have never seen a Development Application processed within 12 weeks, either before or after the introduction of the Integrated Planning Act 1997 (IPA). It is very easy to distort the picture when there is such variability in the range of Development Applications, from relatively simple code assessment