E-alert: Preventing the enforcement of security in a construction setting

This recent decision confirms the difficulties which a party will face when seeking to restrain a call upon a security.

AustraliaReal Estate and Construction

With respect to Portia1, a party seeking to prevent a call upon security is likely to need to mount an argument which is stronger than an appeal to the quality of mercy or to unspecified and unclear negative stipulations.2 The recent Supreme Court of Western Australia decision of CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd3 (CPB v JKC) confirms the difficulties which such a party will face in seeking to restrain a call upon a security.

Background

JKC was the head contractor responsible for the delivery of a substantial oil and gas project in northern Australia. CPB entered into a subcontract with JKC (Subcontract). Article 35.3 of the Subcontract provided:

Contractor [JKC] may have recourse to the Bank Guarantee(s) at any time in order to recover any amounts that are payable by Subcontractor [CPB] to Contractor [JKC] on demand.