Dispute Resolution Options in WA Construction Contracts

When a dispute arises under a WA construction contract, the aggrieved party must stop to seriously consider the options.

AustraliaReal Estate and Construction

Whenever a dispute arises under a construction contract, it is essential for the aggrieved party to stop to consider its options. It may sound obvious, but a party may seriously jeopardise or limit its options by not following this advice.

Most importantly, a party may miss the opportunity to obtain a swift decision on a disputed claim under the Construction Contracts Act 2004 ("the Act").

There are limited circumstances in which a claim may be made under the Act but if the dispute falls within the meaning of a "payment claim", a decision must be given within 28 days of the claim being lodged.

The catch is that there is a strict 28 day time limit from the date on which the payment dispute arose in which to lodge the application.