Developers take heed - Sunset clauses are no longer an excuse to wiggle out of contracts

If you're a developer, this case is a reminder that you can't rely on sunset clauses as a means to rescind a contract.

AustraliaReal Estate and Construction

The addition of section 66ZL of the Conveyancing Act dealing with sunset dates ("New Sunset Clause Law") has attracted a lot of attention, particularly in light of the recent decision of Jobema Developments Pty Limited v Zhu & Ors [2016] NSWSC 3.

A sunset clause within a Contract of Sale specifically addresses the final date ("sunset date") a developer has to complete the project. The inclusion of this clause protects developers who may experience common delays such as problematic weather and financial availability. If the developer has failed to complete the project by the Sunset date, each party is given the opportunity to rescind the contract within 14 days.

Prior to the New Sunset Clause Law, developers were well within their rights to rescind a contract on the expiration of the sunset date. Some property developers exploited this loop hole by rescinding contracts for off-the-plan purchases, only to re-list the same property later at the significantly higher