A contractor gets paid an agreed price for delivery of an agreed
scope of works by an agreed time.
That is of the essence of lump sum construction contracts.
However, it is virtually never the case that these three
essential elements: scope, price and time, look the same at the end
of the job as they did at the start.
Site instructions from the head contractor/principal will change
the scope of the works; extension of time (EOT) claims will change
the time for completion and variation orders will change the
contract price.
Typically, under a lump sum construction contract, the head
contractor/principal can instruct the contractor to do extra work
and to omit certain parts of the original scope of works at any
time. The only limit is that the scope cannot be varied so much
that the works as varied no longer look anything like the works
under the original contract. To take an extreme example, a
principal cannot, by site instruction or variation (unless