Time has become an increasingly common theme in construction
disputes in Australia.
At some stage, most participants in the construction industry
will encounter a dispute about a time limit. Judges of the
Queensland Courts are giving clear warnings to be wary of time
restrictions, whatever their form.
Generally, there are three key timeframes and time limits to be
mindful of when performing construction work. These are:
- CONTRACTUAL NOTICE PERIODS
-
Time bar provisions in construction contracts are extremely
common. They usually operate to require a party
("Party A") to give notice to the other
party ("Party B") of an event (eg
possible delay in reaching practical completion by the date for
practical completion) within a stipulated time period. The Notice
is usually a precondition to Party A having any further rights in
respect of the matter for which notice is required (eg claim an
extension of time ("EOT") or delay
costs).