Caution contractors: Time bars can pack-a-punch!

Time restrictions have become an increasingly common theme in construction industry disputes in Australia.

AustraliaReal Estate and Construction

Time has become an increasingly common theme in construction disputes in Australia.

At some stage, most participants in the construction industry will encounter a dispute about a time limit. Judges of the Queensland Courts are giving clear warnings to be wary of time restrictions, whatever their form.

Generally, there are three key timeframes and time limits to be mindful of when performing construction work. These are:

  1. CONTRACTUAL NOTICE PERIODS
  2. Time bar provisions in construction contracts are extremely common. They usually operate to require a party ("Party A") to give notice to the other party ("Party B") of an event (eg possible delay in reaching practical completion by the date for practical completion) within a stipulated time period. The Notice is usually a precondition to Party A having any further rights in respect of the matter for which notice is required (eg claim an extension of time ("EOT") or delay costs).