ARTICLE · 18 SEPTEMBER 2019

Beware implied terms in building contracts

Article discusses a recent case involved a breach of an implied term to complete building within a reasonable time.

AustraliaReal Estate and Construction

Assisted by Nicole Monteiro

On 27 February, 2019, the Supreme Court of Victoria handed down a decision in Zeng v Leeda Projects Pty Ltd (2019) VSC 106 involving a breach of an implied term to complete building within a reasonable time and determined to award damages against a builder in relation to the homeowner's loss of use and enjoyment of property.

Facts

In 2011, Yun Zeng (Ms Zeng) purchased a whole floor apartment in Melbourne for almost $6,000,000. At the time of purchase, the apartment was a shell and required renovations to be completed prior to Ms Zeng occupying the apartment.

In 2013, Ms Zeng engaged and entered into a building contract with Leeda Projects Pty Ltd (Leeda) to carry out fit-out works which included a residence and private gallery. The building contract provided for the works to be completed by 3 December, 2014. However, the works took an extra 130 weeks to be completed.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from