On 27 February, 2019, the Supreme Court of Victoria handed down
a decision in Zeng v Leeda Projects Pty Ltd (2019) VSC 106
involving a breach of an implied term to complete building within a
reasonable time and determined to award damages against a builder
in relation to the homeowner's loss of use and enjoyment of
property.
Facts
In 2011, Yun Zeng (Ms Zeng) purchased a whole floor apartment in
Melbourne for almost $6,000,000. At the time of purchase, the
apartment was a shell and required renovations to be completed
prior to Ms Zeng occupying the apartment.
In 2013, Ms Zeng engaged and entered into a building contract
with Leeda Projects Pty Ltd (Leeda) to carry out fit-out works
which included a residence and private gallery. The building
contract provided for the works to be completed by 3 December,
2014. However, the works took an extra 130 weeks to be
completed.