ARTICLE · 02 APRIL 2021

Beware: Finalise the terms of your Construction Contracts

The case is a lesson on when a Court will stop you recovering payment if there is no final agreement on contract terms.

AustraliaReal Estate and Construction

In a recent decision of C & V Engineering Pty Ltd v Hamilton & Marino Builders Pty Ltd [2020] NSWCA 103, the New South Wales Court of Appeal has illustrated that it may construe a commercial contract by reference to its "commercial purpose". The decision has important and far reaching implications for those involved in the Building & Construction industry and is a lesson on when a Court will stop you from recovering payment where there is no final agreement on the terms of a contract.

Background

Hamilton and Marino Builders Pty Ltd (Builder) was the Builder contracted to develop a unit complex in Mascot (Project). The Builder reached out to C & V Engineering Pty Ltd (Supplier), requesting the provision of metal joiners for the Project. All negotiations between the parties occurred by way of email correspondence.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from