7/14 Boral Resources (QLD) Pty Ltd v Bundaberg Regional Council [2014] QPEC 8

This was a request by the Applicant for a permissible change to a development approval.

AustraliaReal Estate and Construction

(Rackemann DCJ - 13 March 2014)

Download the judgment

Planning and Environment – where the applicant requested a permissible change to a development approval relating to a quarry – where approval is limited by condition to a time about to expire – where applicant will be seeking a substantive extension to the period for which the approval has effect – where applicant sought interim extension of the permit to enable determination of the substantive application for approval

Facts: This was a request by the Applicant for a permissible change to a development approval relating to the Applicant's quarry located in Bundaberg.

The Applicant's existing approval was the subject of a permissible change request to extend the period to which the approval had effect over the quarry for a further five years.