New deadlines for EP&A Act (NSW) Part 3A: Transitional Project applications

This update explains the new, tighter deadlines which have been imposed in relation to the assessment of such projects.

AustraliaEnvironment

Introduction

On 24 August 2012, significant amendments were made by the NSW Government to the transitional arrangements for major project applications currently before the Department of Planning and Infrastructure (Department) and which continue to be assessed under the repealed Part 3A of the Environmental Planning and Assessment Act 1979 (EP&A Act). This update explains the new, tighter deadlines which have been imposed in relation to the assessment of such projects (known as Transitional Part 3A Projects), and the potentially severe consequences which flow if they are not met.

Overview

Part 3A was repealed on 1 October 2011, and a transitional regime allowed two years from that date for proponents to submit an environmental assessment. These amendments bring forward by 10 months the 'sunset date' for the submission of assessment documents by proponents, to facilitate the Government's aim of completing the assessment of all Transitional Part 3A Projects by 30

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from