Lester v Minister for Planning & Ashton Coal Operations Pty Ltd [2011] NSWLEC 213

This case involved a decision by the NSW Minister of Planning to authorise variations to the Ashton Coal Project in NSW.

AustraliaEnvironment

Introduction

This case involved a decision by the Minister of Planning under the Environmental Planning and Assessment Act, to authorise variations to the Ashton Coal Project being carried out in the Upper Hunter Valley of NSW. The variations that were authorised by the Minister were the instalment of 15 surface gas drainage wells that were to be used to assist the ventilation of gas methane into the atmosphere.

Background

In October 2002, Ashton Coal Operations Pty Ltd, was granted permission (The Principal Consent), to construct an open cut coal mine, an underground (Longwall) coal mine, and the building and operation of associated surface facilities, which were to be later known as the Ashton Coal Project. The approval granted allowed Ashton to extract up to 5.45 million tonnes ("MT") of run-of-mine (" ROM") coal per year from its open cut and underground mining operations, with up to 3.2 MT of coal permitted to be extracted from its underground mining

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from