Quantum meruit: Does your building contract still matter?

When does a claim for QM arise? How does it work? Recent case & key takeaways discussed.

AustraliaCorporate/Commercial Law

A builder's entitlement to recover on a quantum meruit basis is essentially an entitlement to a fair and reasonable sum for works completed and goods provided. This is often used by builders to try to recover monies for out of scope works that were provided but not set out in the original contract.

A claim for quantum meruit may arise if:

  • there is no specified sum to be paid under a contract;
  • there is an express agreement to pay a reasonable sum;
  • work is completed outside the scope of the contract, at the request of the principal/homeowner; and/or,
  • the contract is found to be void or unenforceable.

How does it work?

A typical scenario that leads to a claim for quantum meruit is as follows:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from