Share on LinkedInShare on LinkedIn

ARTICLE · 13 MARCH 2019

Parties To A Contract: Demurrage Liability Under Sales Contracts – Lessons Learned From Gunvor SA v. CruGas Yemen Ltd & CruGas Ltd [2018] EWHC 2061 (Comm)

Two Ocean Tankers' vessels were held in Houthi-controlled Hodeidah, Yemen in 2016 due to a payment dispute.

YemenTransport

Two Ocean Tankers' vessels were held in Houthi-controlled Hodeidah, Yemen in 2016 due to a payment dispute. That dispute – for around US$19 million (excluding interest) – has now been decided by an interesting commercial court decision that highlights the importance of careful wording in demurrage provisions.

Background

The claimant, Gunvor SA (the Seller), entered into a contract (the Sale Contract) in April 2015 with CruGas Yemen Ltd (and/or CruGas Ltd) (the Buyer) for the sale of gasoline in 12 monthly shipments CIF Hodeidah.

In order to fulfil the Sale Contract, the Seller had entered into a long-term contract of affreightment (CoA) with one of its group companies, Clearlake Shipping Pte Ltd (Clearlake), in January 2015. The CoA stated that, when the Seller needed a vessel, Clearlake would charter-in a vessel from the open market and then sub-charter her to the Seller "at cost". In other words, the freight and demurrage rate from each charter would

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.