Within the framework of the Resolution of the Cabinet of
Ministers "On measures to improve the procedure for organizing
and conducting electronic public procurement in the construction
sector" No.55 dated February 5, 2021, a new public procurement
system has been introduced. In particular, there are provided the
following conditions:
- the submission of the general and technical parts of the tender
documentation is not required for conducting an electronic
tender;
- full examination of tender documents and technical
specifications is carried out to assess the volume of goods (works,
services) and their price parameters;
- parties whose volume of financial obligations for the current
year is more than 1.5 times higher than the largest volume
fulfilled by construction and contracting organizations in 1 year
of the last three-year period are not allowed to participate in the
tender;