Source Vagabond Systems (Source) owns a patent directed to flexible water reservoirs, such as for storage in a backpack.

United StatesIntellectual Property

Source Vagabond Sys. Ltd. v. Hydrapak, Inc.

Addressing the reasonableness of a pre-filing claim construction analysis in the context of Rule 11 sanctions, the U.S. Court of Appeals for the Federal Circuit affirmed a lower court's award of Rule 11 sanctions against plaintiff's counsel, finding that the patent holder based its infringement theory on an untenable claim construction and inadequate infringement investigation.  Source Vagabond Sys. Ltd. v. Hydrapak, Inc., Case Nos. 13-1270; -1387 (Fed. Cir., June 5, 2014) (Wallach, J.).

Source Vagabond Systems (Source) owns a patent directed to flexible water reservoirs, such as for storage in a backpack.  According to the patent, a hermetic seal is formed by folding the top of the flexible reservoir over a rod and positioning a long sealer clip sideways over the folded reservoir and rod.  The sealer clip has a slot big enough for the folded reservoir but not the rod.  The pertinent claim element requires the slot to

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from