In this post, we briefly summarize three of the key bid protest decisions published in November 2019.

United StatesGovernment, Public Sector

In this post, we briefly summarize three of the key bid protest decisions published in November 2019.

  • The first two cases relate to the legality of two unusual award methodologies—one examines whether a price/past performance tradeoff methodology violates recent restrictions on the LPTA methodology and the second strikes down a novel approach of selecting the most complementary pair of two proposals.
  • Our third case is a rare sustained protest of a modification to an existing contract that was beyond the scope of the contract and therefore should have been issued as a new procurement.

Inserso Corp., B-417791, B-417791.3, Nov. 4, 2019

Summary

Solicitation for information technology services which provides for award to a technically acceptable offer considered to be the best value based on a tradeoff between price and past performance does not violate restrictions on the use of lowest-priced, technically acceptable award process or criteria.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from