On June 18, 2026, the Public Utility Commission of Texas (PUCT) approved two Electric Reliability Council of Texas (ERCOT) protocol revisions that establish a new “batch” study interconnection framework for large electricity loads of 75 MW or greater. The prior project-by-project approach had generated a growing backlog of unresolved requests, repeated restudies, and prolonged uncertainty in the face of unprecedented growth in large load interconnection requests. The new framework resolves that by delivering a structured, time-bound process with binding interconnection capacity megawatt (MW) allocations expected by April 2027, meaningful optionality in how qualifying large loads structure their interconnection rights, and formal accommodations for co-located and onsite generation arrangements that allow the reduced capacity needs at those interconnections to be reflected in the study process.