On November 3, 2017, FERC largely denied rehearing requests from a group of generation developers ("Generation Developers")...

United StatesEnergy and Natural Resources

On November 3, 2017, FERC largely denied rehearing requests from a group of generation developers ("Generation Developers") regarding the Midcontinent Independent System Operator, Inc.'s ("MISO") revisions to its Generator Interconnection Procedures ("GIP") and its pro forma Generator Interconnection Agreement ("GIA").  With the exception of one issue, FERC otherwise rejected the Generation Developers requests that FERC reconsider prior MISO revisions regarding the efficiency and timeliness of MISO's generator interconnection queue process contained in Attachment X of its Open Access Transmission, Energy and Operating Reserve Markets Tariff ("Tariff").

On January 3, 2017, FERC accepted MISO's proposed revisions to its GIP and its pro forma GIA contained in Attachment X of its Tariff (see January 9, 2017 version of the WER).  Within this order, FERC also accepted MISO's proposed changes to its interconnection procedures.  According to MISO, these changes are

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from