ARTICLE · 07 DECEMBER 2010
5th Circuit Rules CAMR Permitted Power Plant Still Covered by MACT
McGuireWoods LLP
In Sierra Club v. Sandy Creek Energy Associates, Inc., ___ F.3d ___, 2010 U.S. App. 24144 (5th Cir. 2010), issued just before Thanksgiving, that the 5th Circuit Court of Appeals held that an owner of a coal fired power plant being constructed pursuant to a PSD permit was required to obtain a Maximum Available Control Technology (MACT) mercury determination during construction, even if that determination was not necessary at the time the PSD permit was issued.